Vessel Noncompliance Events 2023
Date
In AK?
Violation Code
Event
Vessel
01/01
2.2.26.1(PH)
In January, pH excursions occurred for more than 1% of operating time by 89 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
01/01
2.2.26.1(PH)
In January, pH excursions occurred for more than 1% of operating time by 61 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
01/01
2.2.26.1(PH)
In January, pH excursions occurred for more than 1% of operating time by 334 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
01/08
2.2.26.1
In January, Turbidity exceeded VGP compliance limits on the following days: 08, 15, 22 (twice), 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
01/15
2.2.26.1
In January, Turbidity exceeded VGP compliance limits on the following days: 08, 15, 22 (twice), 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
01/22
2.2.26.1
In January, Turbidity exceeded VGP compliance limits on the following days: 08, 15, 22 (twice), 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
01/29
2.2.26.1
In January, Turbidity exceeded VGP compliance limits on the following days: 08, 15, 22 (twice), 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
02/01
2.2.26.1(PH)
In February, pH excursions occurred for more than 1% of operating time by 92 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
02/01
2.2.26.1(PH)
In February, pH excursions occurred for more than 1% of operating time by 193 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
02/01
2.2.26.1(PH)
In February, pH excursions occurred for more than 1% of operating time by 122 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
02/05
2.2.26.1
In February, Turbidity exceeded VGP compliance limits on the following days: 05
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
02/23
2.2.26.1
In February, Turbidity exceeded VGP compliance limits on the following days: 23
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
03/01
2.2.26.1(PH)
In March, pH excursions occurred for more than 1% of operating time by 113 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
03/01
2.2.26.1(PH)
In March, there were 2 pH excursion(s) >1hr. In addition, pH excursions occurred for more than 1% of operating time by 675 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
03/01
2.2.26.1(PH)
In March, pH excursions occurred for more than 1% of operating time by 10 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
03/09
2.2.26.1
In March, Turbidity exceeded VGP compliance limits on the following days: 09
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
03/11
2.2.26.1
In March, Turbidity exceeded VGP compliance limits on the following days: 11, 30 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
03/21
2.2.26.1
In March, Turbidity exceeded VGP compliance limits on the following days: 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
03/30
2.2.26.1
In March, Turbidity exceeded VGP compliance limits on the following days: 11, 30 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
04/01
2.2.26.1(PH)
In April, pH excursions occurred for more than 1% of operating time by 24 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
04/01
2.2.26.1(PH)
In April, pH excursions occurred for more than 1% of operating time by 7 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
04/12
2.2.26.1
In April, Turbidity exceeded VGP compliance limits on the following days: 12
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/01
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 01 , 03, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/01
2.2.26.1(PH)
In May, there were 4 pH excursion(s)
>1hr.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/01
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/02
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/03
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 01 , 03, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/03
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/03
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 11, 14, 17, 24, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/03
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/04
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 13, 19, 22
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/04
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/04
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 11, 14, 17, 24, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/05
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 05, 12, 16, 17, 24, 26, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/05
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 13, 19, 22
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/05
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/08
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/09
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09, 15, 22, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/09
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09 (twice), 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/09
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/10
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/11
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 11, 25
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
05/11
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/11
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/11
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 11, 14, 17, 24, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/11
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/11
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 11, 18, 25
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/12
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 05, 12, 16, 17, 24, 26, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/12
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 12, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 58% of th
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 58% of th
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/12
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/12
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 12, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/13
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 13, 19, 22
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/14
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 11, 14, 17, 24, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/15
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09, 15, 22, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/15
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09 (twice), 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/15
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/15
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/15
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 15, 19, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/16
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 05, 12, 16, 17, 24, 26, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/16
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/16
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 16
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/16
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/16
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/17
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 05, 12, 16, 17, 24, 26, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/17
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/17
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/17
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 11, 14, 17, 24, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/17
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/18
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/18
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/18
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/18
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 11, 18, 25
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/19
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09 (twice), 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/19
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 13, 19, 22
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/19
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/19
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/19
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 19, 26
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 88% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 88% of the time.
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/19
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 15, 19, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/20
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/20
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/21
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 01 , 03, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/21
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/21
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09 (twice), 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/21
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/21
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/22
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09, 15, 22, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/22
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 13, 19, 22
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/22
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/22
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/24
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 05, 12, 16, 17, 24, 26, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/24
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 11, 14, 17, 24, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/24
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/25
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 11, 25
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 10% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
05/25
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/25
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/25
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/25
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 11, 18, 25
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/26
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 05, 12, 16, 17, 24, 26, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/26
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/26
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 05, 11, 12, 16, 17, 19, 24,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/26
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 19, 26
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 88% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 88% of the time.
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/26
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 12, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/29
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09, 15, 22, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/29
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 08, 11, 16 (twice), 18, 19, 21
(twice), 25 (twice), 26, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/29
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/29
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 11, 14, 17, 24, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/29
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 12, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 58% of th
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 58% of th
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/29
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 15, 19, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 25% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/30
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 09, 15, 22, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 47% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/30
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/30
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 02 (twice), 03 (twice), 04, 09, 10
(twice), 11 (twice), 15, 16, 17, 18
(twice), 20 (twice), 22, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 45% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/31
2.2.26.1
In May, Turbidity exceeded VGP compliance limits on the following days: 05, 12, 16, 17, 24, 26, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
05/31
2.2.26.1
In May, PAH exceeded VGP compliance limits on the following days: 01 , 15, 17 (twice), 18 (twice),
20 (twice), 22, 25, 29, 30 (twice), 31 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time and sootblowing/turbocharger cleaning 1% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/01
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 06, 11, 12, 19, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/01
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/01
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/01
2.2.26.1(PH)
In June, pH excursions occurred for more than 1% of operating time by 15 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/02
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/02
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 06, 11, 12, 19, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/02
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 07, 12, 26, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/02
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 02, 16
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/03
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/04
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 04
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/04
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/04
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 04, 06, 18, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/05
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 09
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/05
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/05
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/06
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/06
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 06, 11, 12, 19, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/06
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/06
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/06
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 04, 06, 18, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/06
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/07
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/07
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 07, 12, 26, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/07
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/08
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/08
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/08
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/09
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 09
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/09
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/09
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/10
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/11
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 11, 25, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/11
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 06, 11, 12, 19, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/11
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/12
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 06, 11, 12, 19, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/12
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/12
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/12
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/12
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 07, 12, 26, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/12
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/12
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 12, 22
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 83% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 83% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/13
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/13
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/13
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/14
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/14
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/14
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 14, 16 (twice), 23, 28 (twice),
29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/15
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/15
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/15
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/15
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 15, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 23% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 23% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/16
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/16
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 02, 16
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/16
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 14, 16 (twice), 23, 28 (twice),
29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/16
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/17
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/18
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/18
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 04, 06, 18, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/18
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/19
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/19
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 06, 11, 12, 19, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/19
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/19
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/20
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 20
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/20
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/20
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/20
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/20
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/21
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/21
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/21
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/21
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/22
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/22
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/22
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/22
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 12, 22
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 83% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 83% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/22
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/23
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/23
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/23
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 14, 16 (twice), 23, 28 (twice),
29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/23
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 23, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/23
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 23
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/24
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/25
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 11, 25, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/25
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 06, 11, 12, 19, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/26
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/26
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/26
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 07, 12, 26, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/26
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 05, 06, 10, 11, 12, 13, 19, 20,
24, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 32% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/26
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 06, 07, 08, 16, 18, 20, 21, 22,
26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/27
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/27
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/27
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 23, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/27
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 04, 06, 18, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/28
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/28
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 28
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/28
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/28
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/28
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 07, 12, 26, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/28
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 14, 16 (twice), 23, 28 (twice),
29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/29
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 11, 25, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/29
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/29
2.2.26.1
In June, PAH exceeded VGP compliance limits on the following days: 01 (twice), 05, 06, 07 (twice), 08
(twice), 12, 13, 14 (twice), 15 (twice),
19, 20, 21 (twice), 22 (twice), 26, 27
(twice), 28, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 1% of the time and sootblowing/turbocharger cleaning 5% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/29
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 08 (twice), 12, 15, 20, 21,
22 (twice), 27, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/29
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 14, 16 (twice), 23, 28 (twice),
29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/29
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 15, 29 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 23% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 23% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/30
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 11, 25, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/30
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 02, 09, 13, 14 (twice), 15, 16,
21, 23, 28 (twice), 29 (twice), 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 6% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/30
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 06, 11, 12, 19, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 74% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/30
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 03, 04 (twice), 09, 12, 17, 18,
22, 23, 26, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 49% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
06/30
2.2.26.1
In June, Turbidity exceeded VGP compliance limits on the following days: 14, 16 (twice), 23, 28 (twice),
29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 12% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/01
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 02, 14, 16, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/01
2.2.26.1(PH)
In July, pH excursions occurred for more than 1% of operating time by 70 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/01
2.2.26.1(PH)
In July, there was 1 pH excursion(s)
>1hr.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/01
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/01
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/01
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/01
2.2.26.1(PH)
In July, pH excursions occurred for more than 1% of operating time by 9 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/01
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/02
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 10, 16, 17, 18, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/02
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 02, 14, 16, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/02
2.2.26.1
In July, PAH exceeded VGP compliance limits on the following days: 02
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 2% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/02
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 60% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 60% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/02
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/02
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/02
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 03 (twice), 04, 16, 21, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/03
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/03
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 03 (twice), 04, 16, 21, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/03
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 05, 06, 10, 20, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/04
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/04
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/04
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/04
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 03 (twice), 04, 16, 21, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/04
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 05, 06, 10, 20, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/05
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/05
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/05
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 05, 06, 10, 20, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/05
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/06
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/06
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/06
2.2.26.1
In July, PAH exceeded VGP compliance limits on the following days: 06
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/06
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 05, 06, 10, 20, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/06
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/07
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/07
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
07/07
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/07
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 07 (twice), 14 (twice), 20
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 26% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 26% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/07
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/08
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/08
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/09
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/09
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/10
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 10, 16, 17, 18, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/10
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/10
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/10
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/10
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 05, 06, 10, 20, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/10
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/11
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 11, 17 (twice), 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/11
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/11
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/11
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 11, 25, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/11
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/12
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/13
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
07/13
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/14
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 02, 14, 16, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/14
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/14
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/14
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 07 (twice), 14 (twice), 20
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 26% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 26% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/14
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/15
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/15
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/16
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 10, 16, 17, 18, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/16
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 02, 14, 16, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/16
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/16
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 03 (twice), 04, 16, 21, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/17
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 10, 16, 17, 18, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/17
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 11, 17 (twice), 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/17
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/18
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 10, 16, 17, 18, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/18
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/18
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/19
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/19
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/20
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/20
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/20
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/20
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 07 (twice), 14 (twice), 20
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 26% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 26% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/20
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 05, 06, 10, 20, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/20
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/21
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/21
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/21
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/21
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 03 (twice), 04, 16, 21, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/21
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/23
2.2.26.1
In July, PAH exceeded VGP compliance limits on the following days: 23 (twice)
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/23
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 23 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/24
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 10, 16, 17, 18, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/24
2.2.26.1
In July, PAH exceeded VGP compliance limits on the following days: 24, 31
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/24
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/24
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/24
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 04, 08 (twice), 09, 10,
16, 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/24
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/25
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/25
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/25
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/25
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/25
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 11, 25, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/26
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/26
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/26
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 06, 12, 13, 18, 19, 20,
25, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 51% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/27
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/27
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/27
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 11, 25, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/28
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 04, 05, 07, 14, 18, 20, 21, 25,
26, 27, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/28
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/28
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/28
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/29
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 02, 14, 16, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/29
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/29
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 07, 08, 09, 10, 11, 14, 21,
24, 25, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/29
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 06, 07, 10, 11, 14, 15,
20, 21, 24, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/30
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 02, 14, 16, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/30
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 03, 06, 10, 11, 15, 19,
20, 21, 24, 25, 26, 27, 28, 29, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 27% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/30
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 03 (twice), 04, 16, 21, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 5% of the
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/30
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 03, 04, 05, 06, 10, 20, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 62% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/30
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/31
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 02, 10, 16, 17, 18, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 9% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/31
2.2.26.1
In July, PAH exceeded VGP compliance limits on the following days: 24, 31
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/31
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 11, 17 (twice), 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
07/31
2.2.26.1
In July, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 8% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
08/01
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 08, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 4% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 4% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/01
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 03, 10 (twice), 17, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/01
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/01
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/01
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 01
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/02
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 08, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 4% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 4% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/02
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/03
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 03, 10 (twice), 17, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/04
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 09, 10, 11, 22, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/04
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/04
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 04
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/05
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 05, 07, 15, 20, 24, 25, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/05
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 05
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/05
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/06
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/07
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 14, 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/07
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 05, 07, 15, 20, 24, 25, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/07
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/07
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/07
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/07
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 11, 18, 21, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/08
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 08, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 4% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 4% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/08
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/09
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 09, 10, 11, 22, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/09
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/09
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09, 11, 13
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 64% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 64% of the time.
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/09
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09, 10, 16, 17, 24 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/10
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 09, 10, 11, 22, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/10
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 10, 16, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 31% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 31% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
08/10
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/10
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 03, 10 (twice), 17, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/10
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/10
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09, 10, 16, 17, 24 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/11
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 11, 12
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/11
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 11, 13, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/11
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 09, 10, 11, 22, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/11
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/11
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/11
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09, 11, 13
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 64% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 64% of the time.
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/11
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 11, 18, 21, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/12
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 11, 12
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/12
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/12
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/13
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 14, 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/13
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 11, 13, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/13
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/13
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/13
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/13
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09, 11, 13
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 64% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 64% of the time.
Correction: System automation adjusted to achieve compliant parameters
Queen Elizabeth
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 8
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/14
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 14, 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/14
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/14
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/15
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 14, 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/15
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 05, 07, 15, 20, 24, 25, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/15
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/15
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 15
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/16
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 10, 16, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 31% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 31% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
08/16
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/16
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09, 10, 16, 17, 24 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/17
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 17, 24
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
08/17
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/17
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 03, 10 (twice), 17, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/17
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 17, 26, 29, 30
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 51% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 51% of the time.
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/17
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09, 10, 16, 17, 24 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/18
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 18
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/18
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/18
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/18
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/18
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 11, 18, 21, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/19
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 14, 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/20
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 05, 07, 15, 20, 24, 25, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/20
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/20
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/21
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 13, 14, 15 (twice), 19, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 20% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/21
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/21
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/21
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 11, 18, 21, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/22
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 09, 10, 11, 22, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/22
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/22
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/22
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 11, 18, 21, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/23
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/23
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/24
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 05, 07, 15, 20, 24, 25, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/24
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 10, 16, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 31% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 31% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
08/24
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 17, 24
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
08/24
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 07, 10, 11, 13, 14, 17, 18,
22 (twice), 23, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/24
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 03, 10 (twice), 17, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/24
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/24
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 09, 10, 16, 17, 24 (twice)
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 33% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/25
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 05, 07, 15, 20, 24, 25, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/25
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/26
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 02, 06, 07 (twice), 10, 11, 12,
18, 20, 21, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 3% of the time and sootblowing/t
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/26
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 17, 26, 29, 30
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 51% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 51% of the time.
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/26
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/27
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 11, 13, 27
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 7% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Miracle
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 10
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/28
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 05, 07, 15, 20, 24, 25, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 30% of the time.
Correction: System automation adjusted to achieve compliant parameters
Grand Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/28
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/29
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 02, 08, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 4% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 4% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/29
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 17, 26, 29, 30
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 51% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 51% of the time.
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/29
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 08, 12, 13, 14 (twice), 15,
20, 21 (twice), 22, 26, 28, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 38% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/29
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 07, 11, 18, 21, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 19% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/30
2.2.26.1
In August, PAH exceeded VGP compliance limits on the following days: 17, 26, 29, 30
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 51% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 51% of the time.
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/30
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 05, 13, 16 (twice), 18, 23,
24, 25, 30
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/31
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 04, 09, 10, 11, 22, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/31
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 (twice), 03, 10 (twice), 17, 24, 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 13% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
08/31
2.2.26.1
In August, Turbidity exceeded VGP compliance limits on the following days: 01 , 31
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 21% of the time.
Correction: System automation adjusted to achieve compliant parameters
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/01
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 06, 13, 15, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/01
2.2.26.1(PH)
In September, pH excursions occurred for more than 1% of operating time by 243 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Ruby Princess
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 14
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/01
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 04 (twice), 09, 12,
15, 18, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/02
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 02, 04, 11, 25
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/03
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 03, 15
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/03
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 03, 10, 21 (twice), 23,
29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/04
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 04
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Carnival Luminosa
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/04
2.2.26.1
In September, PAH exceeded VGP compliance limits on the following days: 04
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 84% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 84% of the time.
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/04
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 02, 04, 11, 25
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/04
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 04 (twice), 09, 12,
15, 18, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/05
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 05, 08, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 91% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 91% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
09/06
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 06, 13, 15, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/07
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 07, 26, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 14% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 14% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/07
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 07, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 7% of the
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 7% of the
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/08
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 05, 08, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 91% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 91% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
09/09
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 04 (twice), 09, 12,
15, 18, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/10
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 03, 10, 21 (twice), 23,
29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/10
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 10, 14
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/11
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 02, 04, 11, 25
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/12
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 04 (twice), 09, 12,
15, 18, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/13
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 06, 13, 15, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/14
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 10, 14
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 10% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/14
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 14, 21, 22, 23, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/15
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 03, 15
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes.
Correction: System automation adjusted to achieve compliant parameters
Carnival Spirit
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Carnival Cruises
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/15
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 06, 13, 15, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/15
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 15, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 46% of th
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 46% of th
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/15
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 04 (twice), 09, 12,
15, 18, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/18
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 04 (twice), 09, 12,
15, 18, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/19
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 04 (twice), 09, 12,
15, 18, 19
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 16% of the time.
Correction: System automation adjusted to achieve compliant parameters
Sapphire Princess
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/21
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 03, 10, 21 (twice), 23,
29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/21
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 15, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 46% of th
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 46% of th
Correction: System automation adjusted to achieve compliant parameters
Nieuw Amsterdam
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 21
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/21
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 14, 21, 22, 23, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/21
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 07, 21
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 7% of the
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 7% of the
Correction: System automation adjusted to achieve compliant parameters
Royal Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/22
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 06, 13, 15, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/22
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 14, 21, 22, 23, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/23
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 03, 10, 21 (twice), 23,
29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/23
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 14, 21, 22, 23, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/25
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 02, 04, 11, 25
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Volendam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/26
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 07, 26, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 14% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 14% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/26
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 14, 21, 22, 23, 26
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 11% of the time.
Correction: System automation adjusted to achieve compliant parameters
Noordam
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/28
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 05, 08, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 91% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 91% of the time.
Correction: System automation adjusted to achieve compliant parameters
Koningsdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: YES
09/28
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 07, 26, 28
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 14% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 14% of the time and sootblowing/
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/29
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 03, 10, 21 (twice), 23,
29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 40% of the time.
Correction: System automation adjusted to achieve compliant parameters
Crown Princess
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 15
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
09/29
2.2.26.1
In September, Turbidity exceeded VGP compliance limits on the following days: 01 , 06, 13, 15, 22, 29
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 18% of the time.
Correction: System automation adjusted to achieve compliant parameters
Discovery Princess
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 22
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
10/01
2.2.26.1
In October, Turbidity exceeded VGP compliance limits on the following days: 01
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Majestic Princess
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Princess
AK Voyages: 20
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
10/04
2.2.26.1
In October, Turbidity exceeded VGP compliance limits on the following days: 04
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Westerdam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
10/05
2.2.26.1
In October, PAH exceeded VGP compliance limits on the following days: 05
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including operating profile and engine load changes. Intermittent short-term exceedances were associated with sootblowing/turbocharger cleaning 100% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
11/01
2.2.26.1(PH)
In November, pH excursions occurred for more than 1% of operating time by 112 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
12/01
2.2.26.1(PH)
In December, pH excursions occurred for more than 1% of operating time by 169 minutes.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Description: Potential causes identified include low buffering water flow, low ambient water pH, transitional buffering conditions and power demand, and sensor related issues potentially impacting the automation system.
Correction: System automation adjusted to achieve compliant parameters.
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
12/17
2.2.26.1
In December, Turbidity exceeded VGP compliance limits on the following days: 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
12/24
2.2.26.1
In December, Turbidity exceeded VGP compliance limits on the following days: 17, 24
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Description: Intermittent short-term exceedances with potential causes including high source water turbidity and impact of engine start up or engine load changes. Intermittent short-term exceedances were associated with EGCS start 67% of the time.
Correction: System automation adjusted to achieve compliant parameters
Eurodam
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO
Operator: Holland America
AK Voyages: 23
EGS System: Open Loop
Discharged into US waters in 2023: YES
Received EPA citations in 2023: NO